nerdexam
GIAC

GCPM · Question #369

calculate the estimated activity durations for your project. If you have an optimistic estimate of 10 days, a pessimistic estimate of 19 days, and a most likely estimate of 13, which of the…

The correct answer is A. 16.5. See the full explanation below for the reasoning.

Question

calculate the estimated activity durations for your project. If you have an optimistic estimate of 10 days, a pessimistic estimate of 19 days, and a most likely estimate of 13, which of the following is the expected activity duration for your project?

Options

  • A16.5
  • B18
  • C17
  • D17.5

How the community answered

(47 responses)
  • A
    83% (39)
  • B
    6% (3)
  • C
    2% (1)
  • D
    9% (4)

Community Discussion

No community discussion yet for this question.

Full GCPM Practice