GCPM · Question #353
What forecasting method would your project use if your project customer requires an autoregressive moving average for performance forecasting?
The correct answer is D. Causal/econometric method. See the full explanation below for the reasoning.
Question
What forecasting method would your project use if your project customer requires an autoregressive moving average for performance forecasting?
Options
- AEnsemble forecasting
- BJudgmental methods
- CTime series method
- DCausal/econometric method
How the community answered
(23 responses)- A4% (1)
- B4% (1)
- C13% (3)
- D78% (18)