nerdexam
GIAC

GCPM · Question #35

relationship, but you require a "waiting time" before the starting of the activity can begin. Which of the following is the best approach to alleviate this issue?

The correct answer is B. Add lag time to the project activities.. See the full explanation below for the reasoning.

Question

relationship, but you require a "waiting time" before the starting of the activity can begin. Which of the following is the best approach to alleviate this issue?

Options

  • AAdd management reserve to the project activities.
  • BAdd lag time to the project activities.
  • CAdd lead time to the project activities.
  • DAdd float to the project activities.

How the community answered

(54 responses)
  • A
    4% (2)
  • B
    72% (39)
  • C
    15% (8)
  • D
    9% (5)

Community Discussion

No community discussion yet for this question.

Full GCPM Practice