The correct answer is A. Integrated change control. See the full explanation below for the reasoning.

Question

You are the project manager of the HJU project for your company. This project will last for 18 months and has a project budget of $567,000. Robert, one of your stakeholders, has introduced a scope change request that will likely have an impact on the project costs and schedule. Robert assures you that he will pay for the extra time and costs associated with the risk event. You tell Robert that the change request may affect more areas of the project than just time and cost and that you are worried about the additional risks the change request will bring. What project management component is responsible for evaluating a change request and its impact on all of the project management knowledge areas?

Options

  • AIntegrated change control
  • BConfiguration management
  • CProject change control system
  • DRisk analysis

Community Discussion

No community discussion yet for this question.

Full GCPM Practice