last for three years and includes 200 stakeholders. How often should the Identify Risks process take place?
The correct answer is A. Throughout the project. See the full explanation below for the reasoning.
Question
last for three years and includes 200 stakeholders. How often should the Identify Risks process take place?
Options
- AThroughout the project
- BOnly once, at the beginning of the project
- CThroughout the executing processes
- DOnce per project phase
How the community answered
(42 responses)- A79% (33)
- B7% (3)
- C2% (1)
- D12% (5)