GCPM · Question #346

last for three years and includes 200 stakeholders. How often should the Identify Risks process take place?

The correct answer is A. Throughout the project. See the full explanation below for the reasoning.

Question

last for three years and includes 200 stakeholders. How often should the Identify Risks process take place?

Options

  • AThroughout the project
  • BOnly once, at the beginning of the project
  • CThroughout the executing processes
  • DOnce per project phase

How the community answered

(42 responses)
  • A
    79% (33)
  • B
    7% (3)
  • C
    2% (1)
  • D
    12% (5)

Community Discussion

No community discussion yet for this question.