You are the project manager for your organization and would like to use a time and materials contract for a small project. What must a time and materials contract have to safeguard the project?
Options
- ATerms for payment
- BApproval from the project sponsor
- CAn approved vendor by a leading trade organization
- DA not-to-exceed clause