You are the project manager for your organization and would like to use a time and materials contract for a small project. What must a time and materials contract have to safeguard the project?

The correct answer is D. A not-to-exceed clause. See the full explanation below for the reasoning.

Question

You are the project manager for your organization and would like to use a time and materials contract for a small project. What must a time and materials contract have to safeguard the project?

Options

  • ATerms for payment
  • BApproval from the project sponsor
  • CAn approved vendor by a leading trade organization
  • DA not-to-exceed clause

How the community answered

(31 responses)
  • A
    10% (3)
  • B
    3% (1)
  • C
    3% (1)
  • D
    84% (26)