GIAC
GCPM · Question #315
You are the project manager of the NHQ Project for your company. You have completed qualitative and quantitative analysis of your identified project risks and you would now like to find an approach…
The correct answer is D. Plan risk responses. See the full explanation below for the reasoning.
Question
You are the project manager of the NHQ Project for your company. You have completed qualitative and quantitative analysis of your identified project risks and you would now like to find an approach to increase project opportunities and to reduce threats within the project. What project management process would best help you?
Options
- AMonitor and control project risks
- BCreate a risk governance approach
- CCreate the project risk register
- DPlan risk responses
How the community answered
(17 responses)- A12% (2)
- C6% (1)
- D82% (14)
Community Discussion
No community discussion yet for this question.