Which of the following are outputs of the Control Scope process? Each correct answer represents a complete solution. Choose all that apply.

The correct answer is A. Work performance measurement B. Project management plan update C. Change request. See the full explanation below for the reasoning.

Question

Which of the following are outputs of the Control Scope process? Each correct answer represents a complete solution. Choose all that apply.

Options

  • AWork performance measurement
  • BProject management plan update
  • CChange request
  • DRequirement documentation

How the community answered

(45 responses)
  • A
    76% (34)
  • D
    24% (11)