Which of the following tasks are performed by the scope development process? Each correct answer represents a complete solution. Choose all that apply.
The correct answer is A. To facilitate clear responsibility assignments B. To define a baseline for performance measurement and control D. To improve the accuracy of cost, duration, and resource estimates. See the full explanation below for the reasoning.
Question
Which of the following tasks are performed by the scope development process? Each correct answer represents a complete solution. Choose all that apply.
Options
- ATo facilitate clear responsibility assignments
- BTo define a baseline for performance measurement and control
- CTo determine whether a scope change has occurred
- DTo improve the accuracy of cost, duration, and resource estimates
How the community answered
(38 responses)- A71% (27)
- C29% (11)