nerdexam
GIAC

GCPM · Question #303

Which of the following processes describes the statement below? "It consists of the processes required to ensure that the project contains all the work required to complete the project effectively."

The correct answer is B. Project scope management. See the full explanation below for the reasoning.

Question

Which of the following processes describes the statement below? "It consists of the processes required to ensure that the project contains all the work required to complete the project effectively."

Options

  • AProject communications management
  • BProject scope management
  • CRisk management
  • DProject human resource management

How the community answered

(34 responses)
  • A
    12% (4)
  • B
    79% (27)
  • C
    6% (2)
  • D
    3% (1)

Community Discussion

No community discussion yet for this question.

Full GCPM Practice