nerdexam
GIAC

GCPM · Question #301

Which of the following is described in the statement below? "It is a group of sequential and related project phases that are defined by the organization and control needs of the management or…

The correct answer is D. Project life cycle. See the full explanation below for the reasoning.

Question

Which of the following is described in the statement below? "It is a group of sequential and related project phases that are defined by the organization and control needs of the management or organizations concerned with the project, the nature of the project itself, and the application area."

Options

  • AVerify scope
  • BProject charter
  • CActivity list
  • DProject life cycle

How the community answered

(25 responses)
  • A
    12% (3)
  • B
    4% (1)
  • C
    12% (3)
  • D
    72% (18)

Community Discussion

No community discussion yet for this question.

Full GCPM Practice