nerdexam
GIAC

GCPM · Question #283

GCPM Question #283: Real Exam Question with Answer & Explanation

The correct answer is A. Mitigation. See the full explanation below for the reasoning.

Question

Marsha is the project manager of the NHQ Project. There's a risk that her project team has identified, which could cause the project to be late by more than a month. Marsha does not want this risk event to happen so she devises extra project activities to ensure that the risk event will not happen. The extra steps, however, will cost the project an additional $10,000. What type of risk response is this approach?

Options

  • AMitigation
  • BTransference
  • CEnhancing
  • DExploiting

Community Discussion

No community discussion yet for this question.

Full GCPM Practice