GCPM · Question #281

GCPM Question #281: Real Exam Question with Answer & Explanation

The correct answer is A. Project scope statement. See the full explanation below for the reasoning.

Question

Which of the following documents refers specifically to the input output mechanism that serves the purpose of providing a narrative description of the sum of the scope of the project?

Options

  • AProject scope statement
  • BProject WBS
  • CProject WBS dictionary
  • DProject charter