Question
project. The office has 200 doors. All doors have to be glassed and painted. Before each door can be painted, the glasses must be fitted in them at least 12 hours before. Alan has arranged these tasks with a finish to start relationship between glassing and painting. What else should Alan do to account for the twelve hours of maintenance time?
Options
- AAlan must schedule all 200 office doors to be glassed first and then schedule all 200 doors to
- BAlan must add twelve hours of lag time to each of the 200 doors painting activity to account for
- CAlan must add twelve hours of lead time to each of the 200 doors painting activity to account
- DAlan must add an intermediary task with duration of twelve hours.