Which of the following is NOT an output of the Control Scope process?

The correct answer is C. Accepted deliverables. See the full explanation below for the reasoning.

Question

Which of the following is NOT an output of the Control Scope process?

Options

  • AProject document updates
  • BWork performance measurements
  • CAccepted deliverables
  • DChange requests

How the community answered

(24 responses)
  • A
    4% (1)
  • B
    13% (3)
  • C
    79% (19)
  • D
    4% (1)