Which of the following process groups starts after the planning phase of a project is over?

The correct answer is D. Execution. See the full explanation below for the reasoning.

Question

Which of the following process groups starts after the planning phase of a project is over?

Options

  • AMonitoring and Controlling
  • BInitiation
  • CTesting
  • DExecution

How the community answered

(26 responses)
  • A
    15% (4)
  • B
    8% (2)
  • C
    4% (1)
  • D
    73% (19)