GIAC
GCPM · Question #27
efficiencies of a project. The table given below has the following related values: Which of the following will be the cost variance (CV) of the project at the current point of time?
The correct answer is C. 30. See the full explanation below for the reasoning.
Question
efficiencies of a project. The table given below has the following related values: Which of the following will be the cost variance (CV) of the project at the current point of time?
Options
- A25
- B-25
- C30
- D-30
How the community answered
(48 responses)- A10% (5)
- B6% (3)
- C81% (39)
- D2% (1)
Community Discussion
No community discussion yet for this question.