GCPM · Question #267

Which of the following contracts is generally considered to be the most risky for the buyer?

The correct answer is A. Cost plus percentage of costs. See the full explanation below for the reasoning.

Question

Which of the following contracts is generally considered to be the most risky for the buyer?

Options

  • ACost plus percentage of costs
  • BCost plus incentive fee
  • CTime and materials
  • DFixed fee

How the community answered

(44 responses)
  • A
    82% (36)
  • B
    2% (1)
  • C
    7% (3)
  • D
    9% (4)