Which of the following is the delay between tasks that have a dependency?
The correct answer is D. Lag time. See the full explanation below for the reasoning.
Question
Which of the following is the delay between tasks that have a dependency?
Options
- AFixed time
- BLead time
- CMean time
- DLag time
How the community answered
(21 responses)- A14% (3)
- B5% (1)
- C5% (1)
- D76% (16)