GCPM · Question #248

Which of the following calculates the earliest and latest starts and finishes of each activity without making the project longer?

The correct answer is C. CPM. See the full explanation below for the reasoning.

Question

Which of the following calculates the earliest and latest starts and finishes of each activity without making the project longer?

Options

  • ARACI
  • BRBS
  • CCPM
  • DWBS

How the community answered

(30 responses)
  • A
    10% (3)
  • B
    3% (1)
  • C
    83% (25)
  • D
    3% (1)