A Project Manager has completed the Scope Planning process. The customer has shortened the schedule by six weeks and decided that the work breakdown structure (WBS. be modified. The Project Manager…
The correct answer is B. Project justification and objectives are not defined. See the full explanation below for the reasoning.
Question
A Project Manager has completed the Scope Planning process. The customer has shortened the schedule by six weeks and decided that the work breakdown structure (WBS. be modified. The Project Manager informs the customer that, by modifying the WBS, the project could be subjected to many problems. Which of the following would not be considered a problem of modifying the WBS?
Options
- AThere are constant changes to the project
- BProject justification and objectives are not defined
- CBudget is not well defined
- DProject may be subject to unforeseen delays
How the community answered
(32 responses)- A3% (1)
- B81% (26)
- C6% (2)
- D9% (3)