nerdexam
GIAC

GCPM · Question #230

The project team members have gotten together at the end of the project to review what happened on the project, discussing what went well and what didn't. They undertake this discussion for the sake…

The correct answer is B. Lessons learned. See the full explanation below for the reasoning.

Question

The project team members have gotten together at the end of the project to review what happened on the project, discussing what went well and what didn't. They undertake this discussion for the sake of future project so that they can repeat the things that worked on the project and eliminate repeating the things that didn't work so well. This is known as what?

Options

  • AContract Closure
  • BLessons learned
  • CClosing the project
  • DContract audit

How the community answered

(31 responses)
  • A
    16% (5)
  • B
    74% (23)
  • C
    6% (2)
  • D
    3% (1)

Community Discussion

No community discussion yet for this question.

Full GCPM Practice