nerdexam
GIAC

GCPM · Question #221

Ned is the project manager for his organization and he's working with management to define the contents of the quality management plan. Ned is concerned that his current project team will need to be…

The correct answer is A. Cost of nonconformance to quality. See the full explanation below for the reasoning.

Question

Ned is the project manager for his organization and he's working with management to define the contents of the quality management plan. Ned is concerned that his current project team will need to be trained on the new software used in the project. He believes that if the project team is not trained on the new software, there will be costly delays and errors within the project execution. What is the term assigned to the costly delays and errors if the project team is not trained on the software?

Options

  • ACost of nonconformance to quality
  • BDirect costs
  • CIndirect costs
  • DCost of quality

How the community answered

(22 responses)
  • A
    86% (19)
  • C
    9% (2)
  • D
    5% (1)

Community Discussion

No community discussion yet for this question.

Full GCPM Practice