Question

Kelly is the project manager for her organization and is managing a project to create new software. In this project some of the project team members have misunderstood the project requirements and have added features to the software that were not requested. Kelly needs to examine the amount of time it took to create these features and determine if the changes should be kept or discarded. What scope control tool and technique would help Kelly determine the magnitude of this variation?

Options

  • AVariance analysis
  • BConfiguration management system
  • CReplanning
  • DChange control system

Unlock GCPM to see the answer

You've previewed enough free GCPM questions. Unlock GCPM for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Full GCPM Practice
Kelly is the project manager for her organization and is managing... | GCPM Q#215 Answer | NerdExam