You have just completed scope verification for your project. This process creates three deliverables for the organization. Which one of the following is not an output of the scope verification…

The correct answer is D. Risk identification. See the full explanation below for the reasoning.

Question

You have just completed scope verification for your project. This process creates three deliverables for the organization. Which one of the following is not an output of the scope verification process?

Options

  • ARequested changes
  • BAccepted deliverables
  • CRecommended corrective actions
  • DRisk identification

How the community answered

(20 responses)
  • A
    10% (2)
  • B
    15% (3)
  • D
    75% (15)