Which of the following are inputs of the Perform Integrated Change control process? Each correct answer represents a complete solution. Choose all that apply.
The correct answer is A. Change request B. Project management plan C. Work performance information. See the full explanation below for the reasoning.
Question
Which of the following are inputs of the Perform Integrated Change control process? Each correct answer represents a complete solution. Choose all that apply.
Options
- AChange request
- BProject management plan
- CWork performance information
- DProject document update
How the community answered
(37 responses)- A84% (31)
- D16% (6)