nerdexam
GIAC

GCPM · Question #205

Which of the following are inputs of the Perform Integrated Change control process? Each correct answer represents a complete solution. Choose all that apply.

The correct answer is A. Change request B. Project management plan C. Work performance information. See the full explanation below for the reasoning.

Question

Which of the following are inputs of the Perform Integrated Change control process? Each correct answer represents a complete solution. Choose all that apply.

Options

  • AChange request
  • BProject management plan
  • CWork performance information
  • DProject document update

How the community answered

(37 responses)
  • A
    84% (31)
  • D
    16% (6)

Community Discussion

No community discussion yet for this question.

Full GCPM Practice