nerdexam
GIAC

GCPM · Question #202

key stakeholders to identify the risks within the project. She is focusing on creating a comprehensive list of project risks, so she is using a facilitator to help generate ideas about project…

The correct answer is A. Brainstorming. See the full explanation below for the reasoning.

Question

key stakeholders to identify the risks within the project. She is focusing on creating a comprehensive list of project risks, so she is using a facilitator to help generate ideas about project risks. Which of the following Identify Risk techniques will she use to accomplish the above task?

Options

  • ABrainstorming
  • BRoot cause analysis
  • CChecklist analysis
  • DDelphi technique

How the community answered

(46 responses)
  • A
    78% (36)
  • B
    7% (3)
  • C
    2% (1)
  • D
    13% (6)

Community Discussion

No community discussion yet for this question.

Full GCPM Practice