key stakeholders to identify the risks within the project. She is focusing on creating a comprehensive list of project risks, so she is using a facilitator to help generate ideas about project…
The correct answer is A. Brainstorming. See the full explanation below for the reasoning.
Question
key stakeholders to identify the risks within the project. She is focusing on creating a comprehensive list of project risks, so she is using a facilitator to help generate ideas about project risks. Which of the following Identify Risk techniques will she use to accomplish the above task?
Options
- ABrainstorming
- BRoot cause analysis
- CChecklist analysis
- DDelphi technique
How the community answered
(46 responses)- A78% (36)
- B7% (3)
- C2% (1)
- D13% (6)