GCPM · Question #200

the project was started earlier, but the project manager working earlier has left. You and your team are involved in estimating the cost of individual work packages or schedule activities with the…

The correct answer is A. Bottom-up. See the full explanation below for the reasoning.

Question

the project was started earlier, but the project manager working earlier has left. You and your team are involved in estimating the cost of individual work packages or schedule activities with the lowest level of detail. Which of the following estimating techniques are you using in the above task?

Options

  • ABottom-up
  • BAnalogous
  • CThree-point
  • DParametric

How the community answered

(17 responses)
  • A
    76% (13)
  • B
    12% (2)
  • C
    6% (1)
  • D
    6% (1)