GIAC
GCPM · Question #200
GCPM Question #200: Real Exam Question with Answer & Explanation
Sign in or unlock GCPM to reveal the answer and full explanation for question #200. The question stem and answer options stay visible for context.
Question
the project was started earlier, but the project manager working earlier has left. You and your team are involved in estimating the cost of individual work packages or schedule activities with the lowest level of detail. Which of the following estimating techniques are you using in the above task?
Options
- ABottom-up
- BAnalogous
- CThree-point
- DParametric
Unlock GCPM to see the answer
You've previewed enough free GCPM questions. Unlock GCPM for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.