GCPM · Question #197

Which of the following processes is used to determine the quantitative or qualitative value of risk associated with the concrete condition and a recognized threat?

The correct answer is D. Risk assessment. See the full explanation below for the reasoning.

Question

Which of the following processes is used to determine the quantitative or qualitative value of risk associated with the concrete condition and a recognized threat?

Options

  • ARisk limitation
  • BIdentify risk
  • CRisk modeling
  • DRisk assessment

How the community answered

(39 responses)
  • A
    15% (6)
  • B
    8% (3)
  • C
    5% (2)
  • D
    72% (28)