In which process group does the project manager and the performing organization choose the vendors the project will use?

The correct answer is C. Executing. See the full explanation below for the reasoning.

Question

In which process group does the project manager and the performing organization choose the vendors the project will use?

Options

  • APlanning
  • BMonitoring and Controlling
  • CExecuting
  • DInitiating

How the community answered

(41 responses)
  • A
    5% (2)
  • B
    12% (5)
  • C
    80% (33)
  • D
    2% (1)