nerdexam
GIAC

GCPM · Question #190

GCPM Question #190: Real Exam Question with Answer & Explanation

The correct answer is A. Acquire Project Team. See the full explanation below for the reasoning.

Question

In which of the following processes is it ensured that the human resources are available and the required team is obtained for completing the project assignments?

Options

  • AAcquire Project Team
  • BDevelop Human Resource Plan
  • CDevelop Project Team
  • DManage Project Team

Community Discussion

No community discussion yet for this question.

Full GCPM Practice