The correct answer is A. Acquire Project Team. See the full explanation below for the reasoning.
Question
In which of the following processes is it ensured that the human resources are available and the required team is obtained for completing the project assignments?
Options
- AAcquire Project Team
- BDevelop Human Resource Plan
- CDevelop Project Team
- DManage Project Team