GCPM · Question #188
GCPM Question #188: Real Exam Question with Answer & Explanation
The correct answer is C. Integrated change control. See the full explanation below for the reasoning.
Question
Thomas is a key stakeholder in your project. Thomas has requested several changes to the project scope for the project you are managing. Upon review of the proposed changes, you have discovered that these new requirements are laden with risks and you recommend to the change control board that the changes be excluded from the project scope. The change control board agrees with you. What component of the change control system communicates the approval or denial of a proposed change request?
Options
- AChange log
- BScope change control system
- CIntegrated change control
- DConfiguration management system