GCPM · Question #182

Your project spans the entire organization. You would like to assess the risk of the project but are worried that some of the managers involved in the project could affect the outcome of any risk…

The correct answer is C. Delphi technique. See the full explanation below for the reasoning.

Question

Your project spans the entire organization. You would like to assess the risk of the project but are worried that some of the managers involved in the project could affect the outcome of any risk identification meeting. Your worry is based on the fact that some employees would not want to publicly identify risk events that could make their supervisors look bad. You would like a method that would allow participants to anonymously identify risk events. What risk identification method could you use?

Options

  • ASWOT analysis
  • BIsolated pilot groups
  • CDelphi technique
  • DRoot cause analysis

How the community answered

(45 responses)
  • A
    4% (2)
  • B
    11% (5)
  • C
    78% (35)
  • D
    7% (3)