Question
Holly is the project manager of a project in a functional environment. Jason, the functional manager, has just informed Holly a new requirement that he has approved for the project. Holly documents the change and updates the project scope. What document should Holly also update in light of this change?
Options
- AProject time estimate
- BProject WBS
- CProject cost estimate
- DProject risk plan