GCPM · Question #18
Holly is the project manager of a project in a functional environment. Jason, the functional manager, has just informed Holly a new requirement that he has approved for the project. Holly documents…
The correct answer is B. Project WBS. See the full explanation below for the reasoning.
Question
Holly is the project manager of a project in a functional environment. Jason, the functional manager, has just informed Holly a new requirement that he has approved for the project. Holly documents the change and updates the project scope. What document should Holly also update in light of this change?
Options
- AProject time estimate
- BProject WBS
- CProject cost estimate
- DProject risk plan
How the community answered
(38 responses)- A5% (2)
- B71% (27)
- C8% (3)
- D16% (6)