nerdexam
GIAC

GCPM · Question #174

GCPM Question #174: Real Exam Question with Answer & Explanation

Sign in or unlock GCPM to reveal the answer and full explanation for question #174. The question stem and answer options stay visible for context.

Question

Robert is the project manager of the NHH Project and is working with his project team to create the WBS for his organization. He has a project scope statement that needs to be broken down into smaller, more manageable components. He would like to organize the components by project phase to help organize the deliverables created in each phase of the project. What is the tool and technique called that breaks down the project scope into the WBS?

Options

  • ADecomposition
  • BRequirements breakdown
  • CFunctional analysis
  • DSubdivision

Unlock GCPM to see the answer

You've previewed enough free GCPM questions. Unlock GCPM for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Full GCPM Practice