Question
Robert is the project manager of the NHH Project and is working with his project team to create the WBS for his organization. He has a project scope statement that needs to be broken down into smaller, more manageable components. He would like to organize the components by project phase to help organize the deliverables created in each phase of the project. What is the tool and technique called that breaks down the project scope into the WBS?
Options
- ADecomposition
- BRequirements breakdown
- CFunctional analysis
- DSubdivision
How the community answered
(19 responses)- A79% (15)
- B11% (2)
- C5% (1)
- D5% (1)