between two activities. She wants to delay the start of the second activity by 19 hours. What scheduling component should Jane add to the second activity?
The correct answer is C. Lag time. See the full explanation below for the reasoning.
Question
between two activities. She wants to delay the start of the second activity by 19 hours. What scheduling component should Jane add to the second activity?
Options
- AProject float
- BLead time
- CLag time
- DProject slack
How the community answered
(44 responses)- A7% (3)
- B14% (6)
- C75% (33)
- D5% (2)