Which of the following is a method of planning and managing projects that puts more emphasis on the resources required to execute project tasks?
The correct answer is C. Critical Chain Project Management (CCPM). See the full explanation below for the reasoning.
Question
Which of the following is a method of planning and managing projects that puts more emphasis on the resources required to execute project tasks?
Options
- ADynamic Systems Development Method (DSDM)
- BCritical Path Method (CPM)
- CCritical Chain Project Management (CCPM)
- DLinear scheduling method (LSM)
How the community answered
(44 responses)- A5% (2)
- B9% (4)
- C80% (35)
- D7% (3)