GCPM · Question #15

You work as the project manager for Bluewell Inc. You are working on NGQQ Project for your company. You have completed the risk analysis processes for the risk events. You and the project team have…

The correct answer is C. Risk transference. See the full explanation below for the reasoning.

Question

You work as the project manager for Bluewell Inc. You are working on NGQQ Project for your company. You have completed the risk analysis processes for the risk events. You and the project team have created risk responses for most of the identified project risks. Which of the following risk response planning techniques will you use to shift the impact of a threat to a third party, together with the responses?

Options

  • ARisk acceptance
  • BRisk avoidance
  • CRisk transference
  • DRisk mitigation

How the community answered

(56 responses)
  • A
    7% (4)
  • B
    14% (8)
  • C
    77% (43)
  • D
    2% (1)