GCPM · Question #142

Which of the following methods tends to keep the resources levelly loaded, but requires the resources to be flexible in their start times and to quickly switch between tasks and task chains to keep…

The correct answer is A. Critical Chain method. See the full explanation below for the reasoning.

Question

Which of the following methods tends to keep the resources levelly loaded, but requires the resources to be flexible in their start times and to quickly switch between tasks and task chains to keep the whole project on schedule?

Options

  • ACritical Chain method
  • BCritical Path method
  • CResource utilization
  • DResource leveling heuristics

How the community answered

(30 responses)
  • A
    80% (24)
  • B
    7% (2)
  • C
    10% (3)
  • D
    3% (1)