GCPM · Question #135

In which of the following contract types, the seller is reimbursed for all allowable costs for performing the contract work and receives a fixed fee payment which is calculated as a percentage of…

The correct answer is A. Communications Management Plan, Execution Process group. See the full explanation below for the reasoning.

Question

In which of the following contract types, the seller is reimbursed for all allowable costs for performing the contract work and receives a fixed fee payment which is calculated as a percentage of the initial estimated project costs?

Options

  • ACommunications Management Plan, Execution Process group
  • BCommunications Management Plan, Planning Process Group
  • CProject Management Plan, Planning Process Group
  • DProject Management Plan, Initiating Process Group

How the community answered

(30 responses)
  • A
    83% (25)
  • B
    10% (3)
  • C
    3% (1)
  • D
    3% (1)