You are the project manager for your organization. Your organization manages projects for other companies. You will be soon managing a project for the JUH Company. What document do you need first to…

The correct answer is D. Contract. See the full explanation below for the reasoning.

Question

You are the project manager for your organization. Your organization manages projects for other companies. You will be soon managing a project for the JUH Company. What document do you need first to help to develop the project charter?

Options

  • ABusiness requirements
  • BFunctional requirements
  • CPreliminary project scope statement
  • DContract

How the community answered

(17 responses)
  • A
    6% (1)
  • B
    12% (2)
  • C
    6% (1)
  • D
    76% (13)