Which of the following are the tasks performed by the Work breakdown structure (WBS)? Each correct answer represents a complete solution. Choose all that apply.
The correct answer is A. It separates the major project deliverables into smaller components to improve the accuracy B. It defines assignable resources, such as personnel, from a functional point of view. D. It provides a mechanism for performance measurement and control. See the full explanation below for the reasoning.
Question
Which of the following are the tasks performed by the Work breakdown structure (WBS)? Each correct answer represents a complete solution. Choose all that apply.
Options
- AIt separates the major project deliverables into smaller components to improve the accuracy
- BIt defines assignable resources, such as personnel, from a functional point of view.
- CIt provides a mechanism for collecting and organizing actual costs.
- DIt provides a mechanism for performance measurement and control.
How the community answered
(33 responses)- A79% (26)
- C21% (7)