limited amount of detailed information about the project or program. Which of the following estimation techniques will you use to accomplish the task?

The correct answer is C. Analogous. See the full explanation below for the reasoning.

Question

limited amount of detailed information about the project or program. Which of the following estimation techniques will you use to accomplish the task?

Options

  • AThree-point
  • BBottom-up
  • CAnalogous
  • DParametric

How the community answered

(51 responses)
  • A
    4% (2)
  • B
    10% (5)
  • C
    84% (43)
  • D
    2% (1)

Community Discussion