for your team in advance. Which of the following techniques of the Acquire project team has been used in the above scenario?

The correct answer is A. Pre-assignment. See the full explanation below for the reasoning.

Question

for your team in advance. Which of the following techniques of the Acquire project team has been used in the above scenario?

Options

  • APre-assignment
  • BAcquisition
  • CVirtual team
  • DNegotiation

How the community answered

(28 responses)
  • A
    82% (23)
  • B
    4% (1)
  • C
    4% (1)
  • D
    11% (3)

Community Discussion

No community discussion yet for this question.