GIAC
GCPM · Question #101
several scope changes that will drastically alter his project plan. There are also some changes caused to the project risks, communication, and vendors. Which of the following should also be updated…
The correct answer is B. Quality baseline. See the full explanation below for the reasoning.
Question
several scope changes that will drastically alter his project plan. There are also some changes caused to the project risks, communication, and vendors. Which of the following should also be updated based on the above scope changes?
Options
- AProcess improvement plan
- BQuality baseline
- CVendor selection process
- DStakeholders identification
How the community answered
(36 responses)- A6% (2)
- B78% (28)
- C3% (1)
- D14% (5)
Community Discussion
No community discussion yet for this question.