hierarchical list of resources related by function and resource type that is used to facilitate planning and controlling of project work. Which of the following components of project management will y

The correct answer is B. RBS. See the full explanation below for the reasoning.

Question

hierarchical list of resources related by function and resource type that is used to facilitate planning and controlling of project work. Which of the following components of project management will you use to accomplish the above task?

Options

  • APERT chart
  • BRBS
  • CGantt chart
  • DWBS

How the community answered

(38 responses)
  • A
    8% (3)
  • B
    74% (28)
  • C
    3% (1)
  • D
    16% (6)