When can the building and testing of a Change begin?
The correct answer is C. As soon as the Request for Change (RFC) has been formally authorized. See the full explanation below for the reasoning.
Question
When can the building and testing of a Change begin?
Options
- AAs soon as the impact analysis has been discussed by the members of the Change Advisory
- BAs soon as there is a correct network plan for the change
- CAs soon as the Request for Change (RFC) has been formally authorized
- DAs soon as the Request for Change (RFC) has been classified
How the community answered
(45 responses)- A2% (1)
- B13% (6)
- C78% (35)
- D7% (3)