EX0-112 · Question #50
Which activities are not in a transition plan?
The correct answer is A. the activities that are required for a successful preparation of the implementation. Option A describes preparation activities, which belong in an implementation or preparation plan - not the transition plan itself. The transition plan focuses on what happens during the actual transition/rollout, not the groundwork laid beforehand. Options B and C are both…
Question
Which activities are not in a transition plan?
Options
- Athe activities that are required for a successful preparation of the implementation
- Bthe generic activities that have to be performed at all locations where the system is
- Cthe specific activities that have to be performed at a specific location during transition
How the community answered
(53 responses)- A81% (43)
- B6% (3)
- C13% (7)
Explanation
Option A describes preparation activities, which belong in an implementation or preparation plan - not the transition plan itself. The transition plan focuses on what happens during the actual transition/rollout, not the groundwork laid beforehand.
Options B and C are both legitimate contents of a transition plan: generic activities (B) apply across all deployment locations, while specific activities (C) address what each individual location needs during its own transition. Together, they cover the full scope of the transition execution.
Memory tip: Think of "transition" as the moment of change, not the preparation for change. If it happens before the system goes live, it belongs in a preparation plan; if it happens while rolling out the system site by site, it belongs in the transition plan.