EX0-112 · Question #43
Which process produces an end user training for a new release of an application?
The correct answer is B. Prepare transition. "Prepare transition" is correct because this process covers all readiness activities needed before a new release goes live - including creating and delivering end user training. It ensures users are equipped to work with the new system before the actual switch happens. Why the…
Question
Which process produces an end user training for a new release of an application?
Options
- ATransition
- BPrepare transition
- CDesign non-automated information systems
How the community answered
(23 responses)- A9% (2)
- B87% (20)
- C4% (1)
Explanation
"Prepare transition" is correct because this process covers all readiness activities needed before a new release goes live - including creating and delivering end user training. It ensures users are equipped to work with the new system before the actual switch happens.
Why the distractors are wrong:
- A. Transition is the execution phase where the new release is actually deployed and handed over to users - training should already be complete by this point, not produced during it.
- C. Design non-automated information systems is a design-stage process focused on defining how non-automated workflows operate; it has no responsibility for training production.
Memory tip: Think of "Prepare transition" as the "get ready" phase - you train users before you flip the switch, not during or after. If training were produced in Transition itself, users would go live unprepared. The word "Prepare" signals pre-go-live readiness activities, and training is a core part of that readiness.