EX0-112 · Question #25
What is an activity of the process Specify information requirements?
The correct answer is C. validating and approving specifications. Validating and approving specifications (C) is correct because "Specify information requirements" is fundamentally about defining, refining, and confirming what information a system or process needs - and validation/approval is the quality gate that closes that specification…
Question
What is an activity of the process Specify information requirements?
Options
- Adecision-making about the execution of changes
- Bidentifying IT-solutions
- Cvalidating and approving specifications
How the community answered
(37 responses)- A3% (1)
- B5% (2)
- C92% (34)
Explanation
Validating and approving specifications (C) is correct because "Specify information requirements" is fundamentally about defining, refining, and confirming what information a system or process needs - and validation/approval is the quality gate that closes that specification loop, ensuring stakeholders agree the requirements are complete and accurate.
Why the distractors are wrong:
- A (decision-making about executing changes) belongs to a change management process, not requirements specification. Deciding whether to execute a change happens after requirements are already established.
- B (identifying IT-solutions) is part of solution design or architecture activities. Specification of information requirements intentionally avoids prescribing solutions - it captures what is needed, not how to build it.
Memory tip: Think of "Specify" as a three-step loop - draft → validate → approve. Option C maps directly onto the last two steps. If an answer sounds like managing change (A) or picking technology (B), it's from a different process entirely.
Topics
Community Discussion
No community discussion yet for this question.